Cheshire East has £12.7m of a £21.7m housing grant left for Handforth Garden Village and must spend it by 31 March 2027. Cabinet decides on 26 November.
Cheshire East Council has five months to spend more than half of a £21.7 million government grant for the Garden Village at Handforth, or risk losing it. Its Cabinet will be asked on Thursday 26 November to approve a fast-tracked list of work to use the money before the deadline.
The same report recommends that work on one of the scheme’s main A34 junctions, named as “Phase 1A North (A34 Dumbbell Roundabout)”, should not go ahead under the council’s existing contract.
Overview
- The grant: Homes England’s Housing Infrastructure Fund gave £21.7 million for the Garden Village. By September 2026, £8.952 million had been claimed.
- What is left: £12.748 million, which has to be spent and claimed by 31 March 2027.
- The plan: a list of design work, enabling works and statutory payments worth about £15 million, more than the grant left, to be done in priority order.
- The A34 roundabout: remaining design work under the current contract stops, and Phase 1A North will not be built under that contract.
- The decision: Cabinet, Thursday 26 November, 10.30am.
What the report says
The report, reference C/118/26-27, is from the council’s portfolio holder for planning, housing and regeneration (Cabinet report, 26 November 2026). It says Homes England has agreed “in principle” to change the funding agreement. That would let the council redirect the rest of the grant to work it can finish before the end of March.
The council’s finance officer is blunt about the timetable. More than half the grant “would need to be supported by eligible expenditure, properly evidenced and claimed within the remaining five months”. The report calls that “exceptionally challenging”.
The deadline has already been moved once. The report says officers do not think a second extension is realistic, and Cabinet is told to treat 31 March 2027 as final.
The £15 million list
The full spending list, Appendix A, is not public. The council has marked it exempt because it contains commercial information. The report describes it as:
- infrastructure design
- enabling works
- statutory payments
- other work “required to maintain delivery momentum”
The list adds up to about £15 million, against roughly £12.4 million of grant expected to remain after the next claim. The finance officer says it “must therefore be managed as a prioritised programme of potential activity, not as authority to spend £15m”. Anything that would add to the council’s borrowing has to come back through the normal budget process.
Why the A34 roundabout work is stopping
The council’s Initial Preparation and Infrastructure Works contract covers the first roads and junctions on the site. A review has concluded that the remaining design work under it should be “curtailed”. Phase 1A North, the A34 Dumbbell Roundabout, “shall not proceed under the existing contractual arrangements”.
The report says the council keeps the benefit of the work done so far, and that “alternative delivery arrangements are being progressed”. The detail is in Appendix B, which is also exempt. The report does not say when the roundabout will now be built, or by whom.
Work began in August on a new gateway entrance to the site from the A34, which kept the 2023 planning permission alive, as we reported at the time. The report does not say how that work relates to Phase 1A North.
The wider money picture
The Garden Village sits in the council’s capital programme with a budget of £64.707 million. Spending to 31 March 2026 was £13.025 million, paid for by borrowing and the grant.
If money is spent and later found not to qualify for the grant, the council would have to cover it, “most likely” with more borrowing. The report warns that this would put “additional pressure on the Council’s already constrained financial position”.
The scheme is for about 1,500 homes on land east of the A34 and south of the A555, with a through school, a country park and employment land. The council owns about 70% of the site. Since 2025 it has been working with MADE Partnership, the developer formed by Barratt Redrow, Homes England and Lloyds Banking Group, on how to deliver it.
MADE’s application to change the 2023 permission, 26/2366/VOC, went to the Strategic Planning Board on Wednesday 18 November. We set out the changes before the meeting. The council had not published the board’s decision when we checked on 20 November.
What it means for you
If you live in Handforth or Wilmslow, the money decision matters more than it sounds. The grant pays for roads and junctions that would otherwise fall to the council, to MADE, or to future land sales. Losing part of it could slow the scheme.
The A34 is where you are most likely to notice any change. The report confirms the Phase 1A North roundabout will not be built under the current contract. It does not give a new date.
Cabinet meets at 10.30am on Thursday 26 November. The papers are on the meeting page. The report is listed as not a key decision, which means it does not need advance notice on the forward plan.